WORK AREA 1: PROJECT MANAGEMENT |
|
|
|
|
|
---|---|---|---|---|---|
Work Item | Description | Deliverable | Due Date | Owner | Status |
PM1: Secure PEER Funding | ISOC have agreed to provide funding for the PEER project, with TERENA | Funding Letter from ISOC to TERENA | 12/12/10 | LL | Complete |
PM2: PEER Project Plan | Develop a full project plan for PEER | Project Plan 'live" on I2 wiki, hard copy delivered to TERENA | 31/01/11 | NH / LJ | In Progress Complete |
PM3: Contractual Arrangements | Using common TERENA contractual template, put in place contracts with YACO, EDINA, JISC Advance, WAYF.dk (Leif?) | Signed contracts with TERENA | 28/02/11 | LF | In Progress |
PM4: Management Liaision | Arrange biweekly calls between project management liaisons (NH, LJ, LL, LF) | No deliverable | No due date | NH / LJ | Ongoing |
...
WORK AREA 2: PEER SOFTWARE DEVELOPMENT User Interface |
|
|
|
|
|
---|---|---|---|---|---|
Work Item | Description | Deliverable | Due Date | Owner | Status |
PSD1: Initial Architecture | Create an initial architecture proposal for PEER | Architecture Documentation | 12/12/20 | LJ | Complete |
...
WORK AREA 3:
...
PEER Storage Engine and Metadata Validator
No work is scheduled under this work area for phase 1.
...