Timeline: September 2011 - December 2011
Description
Phase 3 of the PEER project will test PEER 'in anger', with three live implementations. SWAMID will operate an instance of PEER for internal use,
NORDUnet will operate a public instance of PEER and the UK will run a public instance of PEER. This phase will eventually feed-in to a sustainability plan for PEER to be considered by REFEDS and other interested parties.
Work Areas
WORK AREA 1: PROJECT MANAGEMENT |
|
|
|
|
|
---|---|---|---|---|---|
Work Item | Description | Deliverable | Due Date | Owner | Status |
PM4: Management Liaision | Arrange biweekly calls between project management liaisons (NH, LJ, LL, LF) | No deliverable | No due date | NH / LJ | Ongoing |
PM5: PEER Sustainability Model | Develop a proposal for PEER service sustainability | Report on sustainability | 31/12/11 | NH | Not started |
WORK AREA 2: PEER User Interface
No work items are scheduled for this phase.
WORK AREA 3: PEER Storage Engine and Metadata Validator
No work items are scheduled for this phase.
WORK AREA 4: SUPPORT AND DELIVERY |
|
|
|
|
|
---|---|---|---|---|---|
Work Item | Description | Deliverable | Due Date | Owner | Status |
SAD5: PEER promotion | Promotion of PEER at appropriate events | No deliverable, time can be claimed | ongoing | NH / LF | Not started |
SAD6: Service Instances | Run 3 live instances of PEER and provide feedback to sustainability planning | Input documentation for sustainability planning | 31/12/11 | LJ | Not started |