The first step is to provide support for requested attributes in InCommon metadata. An initial implementation of SP Attribute Requirements an administrative user interface was debuted at the Spring 2011 Internet2 Member Meeting. Deployment throughout the Federation Production deployment of this interface will commence in June 2011 and ramp up as we approach the new 2011–2012 academic year.

The second step is to provide support for user consent in the IdP software. SWITCH, the Swiss federation, has led the way by developing a Shibboleth add-on called uApprove that is widely deployed within the SWITCH federation. InCommon IdPs can use uApprove today; a few InCommon early-adopter IdPs have already done so.

...